PIR not getting consume .

To PP Gurus

I am in process industry project .I am using 40 & 10 strategy for different product .But I am facing problem .I am running MRP for HALB-1 which will create planned orders then i will convert all planned order to process order .

Now when I am doing GRN Receipt of this process order stock will show in MD04 system will show this stock against LSF or VSF reqmnt ..I will consume this material for FERT-1 .After consuming this HALB-1 for FERT-1 if i refresh MD04 screen of HALB-1 system will show me LSF reqmnt as it is .So when I run MRP for my next reqmnt system create again planned order .for my orignal reqmnt of this month also .

My problem is PIR are not getting consume against dep reqmnt or order resevation or any other MRP element .Every month i have to delete previous reqmnt ..

I have checked with consumption mode MRP-3 view still not work .I also checked with In MD61 screen item tab 1 field consumption where i put consume any MRP element .still its not working .




I not able to understand why we need to create PIR for HALB1. HALB1 is used in HALB2 & FERT, so its dependent requirements would be transferred to HALB1 and MRP would create planned orders based on the requirements from FERT and HALB2.

I would suggest you not to maintain any PIR for HALB1.