on 04-23-2009 10:52 AM
Hello every one in my project i have got a requirement in which in activities i should not post any internal cost to the networks but we have to book the time sheet through cats. I think we can do it through some change in activity type. (In short its like normal project but suddenly my management dont wanna put internal cost to the project) Kindly give me some solution on this.
With Regards
Abhishek Sinha
Idhasoft, India
Hi,
Can you please explain your question in detail?it is not clear.
Muzamil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Sir,
The que is i got requirement yesterday in which now i dont have to book any cost through internal activities bcoz as internal cost we are having salary of the consultants. Now HR dont wanna disclose these figures in project. I put 0 in trnsaction KP26 . so that cost can be 0. but when i m trying to run transn CAT2 error message is coming . It means i have to put some figure in KP20 more than 0. Is there any possiblity that i can maintain 0 in KP26. In project i will only book external activity cost and revenues.
With Regards
Abhishek Sinha
Idhasoft, India
In case you want to use the work center then dont assign activity types to the work center, and if you do not want to remove the activity type from the work center just dont assign the activity type in the activity detail screen in the network.
alternatively you can try activity type category 4 in KL02. (not sure whether this will help)