on 04-23-2009 9:53 AM
Hi Experts,
We have an issue where user is not able to do any changes on network header and activity level (e.g they are setting system status Lock) and getting an error message "please do not use diffrent profit centers in project structurers".
When we checked we have found that it is because of validation on network header and activity level "Validate PRCTR in Network header is the same as in project definition".
Here projects are copied from stanard template and user have copied this project from old template becuse of which he is successfully saved the project without getting any error in the first place inspite of having a different profit centers in same project structure.
could you please help me in this as it is not allowing any changes on network and activity level.
Regards,
Abdul Rehman Shaikh
hi
you cannot change the profit center you have to delete this network and create new network
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Goto network change cn22 > assignments tab and enter the same profit center as in the project definition.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.