currently i am facing LIV cancellation issues in MM module which is link to budget exceeding in previous year.
i was told that i can use CJBV to deactivate the availablility control, then perform the LIV cancellation, then use CJBN to re-activate the availability control.
Is there any impact or issue to the project budget/commitmemt?
Thanks
If u deactivate, there wil not be any control on project budget.
Actual Cost can overshoot the budget.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi ,
After deactivating AVAC u can book actual / commitement cost more than budgeted cost for the WBS.
Wht is LIV cancellation ?
Rgds
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.