Availability Date

Former Member
0 Kudos

Hi Experts,

May I kindly ask what are the factors affecting the availability date during the Capable to Promise check? This is because when a sales order is created in R/3, the confirmed date created during the check for the required quantity is 4 months after. Which is too far in the future.

Really hoping for your help. Thank you.

Sincerely,

Ria

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Ria,

Just check in heuristic settings for SAP_PP_CTP, scheduling offset is defined. It will try to fix the date/time as per earliness/lateness.

Regards

R. Senthil Mareeswaran.

Former Member
0 Kudos

Hi Senthil,

Thanks a lot.

Sincerely,

Ria

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Ria,

1. You create the sales order in the R/3 System entering the desired quantity and the desired date.

2. In SAP APO, an ATP check is carried out for the requirement online. Here, the system checks whether the quantity can be confirmed on the requirements date.

3. If the desired quantity cannot be confirmed or can only partially be confirmed, SAP APO accesses production planning and detailed scheduling (according to the Customizing settings in the check instructions).

4. SAP APO creates a receipt element (planned order or stock transport requisition) for the missing quantity of the product in the sales order item. The system looks the up the available capacity and executes production planning, that is, the order is scheduled and the required components are calculated.

○ The order is planned using the bucket-oriented capacity check, taking into account the available capacity. Here, the system calculates the availability date of the product. You can also define that the system is to take the availability of important components into account. In this case, scheduling is executed at multi-levels. When calculating the availability date, the system takes account of component availability.

If you find out that the preceding CTP check has not created the desired planned orders, for example, only created planned orders in the past. Then you can execute the heuristic (SAP_CTP_DLG) from the product view. You can use this heuristic interactively to create receipts with better timing.

See also: Planning in the CTP Process with Planning Procedure 3

○ Capacity check using capacity reservation.

In addition to capacity check, the system also considers the reservations maintained on the resource while scheduling operations.

See also: Capacity Reservation and Maintaining Capacity Reservations.

5. At the same time, temporary requirements are created for the product to protect the planned order from competing sales orders. The function

6. of the temporary requirements corresponds to the external temporary quantity assignments of the ATP. See also: Reserving Temporary Planned Orders by Temporary Requirements

7. The result (confirmed quantity and date) is displayed in the delivery proposal screen. You accept the confirmation and return to the sales order entry in the R/3 System.

8. You save the sales order.

9. The sales order is posted in the R/3 System and then in SAP APO. In SAP APO, the temporary planned orders are converted into permanent planned orders. The temporary quantity assignments are deleted and the ATP time series are updated.

10. If, in Customizing for PP/DS, in the IMG activity Maintain Global Parameters and Default Values, you defined the setting Always create transfer results in the fields Transfer to R/3 and Transfer to R/3 External Procurement, the system sends an event from SAP APO to the R/3 System when posting the sales order.

11. After posting the planned order in the R/3 System, the planned order number is transferred to SAP APO and the planned order number in SAP APO is updated.

Regards

R. Senthil Mareeswaran.

Former Member
0 Kudos

Hi Senthil,

Thanks a lot for your reply. However, it seems weird that APO is proposing a confirmed date of 4 months in advance considering that the quantity procured is small and the resource is not yet utilized.

Should there be other things I should look into?

Thanks again.

Sincerely,

Ria