Hi Folks,
I have a project and in that one of the activities when used in the timesheet for booking times returns with a warning messange Syatem status CNF is active. I can see that the status says confirmed. How can i get rid of this error message?
Regards,
Chinmaya
Cancel the confirmation using CN29. and then try booking time.