Process control 2.5 Organization structure "create"button grayed

Former Member
0 Kudos

Hi All,

We have installed GRC Process control 2.5.and configured NWBC

sucessfully.

When we are opening Compliance Structure>>Organization Structure..and

we found "create & Open" button is grayed.

I have assigned the following roles to my user id.

SAP_GRC_SPC_ALL

SAP_GRC_SPC_BUSINESS_USER

SAP_GRC_SPC_CUSTOMIZING

SAP_GRC_SPC_DISPLAY

SAP_GRC_SPC_SETUP

As per the security guide of GRC PC 2.5 if the user is having SAP_GRC_SPC_ALL role will super user.but this authorization NOT is working .

I have activated all the BC sets as per the note:"1234713"

Is there any step i have missed out....

Kindly help me..

Thanks & Regards

Gangadhar

Accepted Solutions (1)

Accepted Solutions (1)

0 Kudos

Execute the Transaction(Tcode): GRPC_STR_CREATE

"Create Root Organizational Object" - if one is not defined already and specify validity dates.

For Eg:

Corp Node

Org 1

now when you logon from frontend, you should be able to see and create new organizations.

Note:

You will not be able to create new Organizations w/o defining the Top level Corp node in the PC

backend.

Regards

Rohit

Answers (2)

Answers (2)

former_member192417
Active Participant
0 Kudos

HI Gangadhar

Just for your information, dont use NWBC and GRPC_STR_CHANGE at same time.Then it will lock the organization in the frontend.and you wont be able to add or edit any Organization.

Thanks

Debraj

Former Member
0 Kudos

Hi All,

Thanks a lot for your valuable inputs, Now i have Got procedure.

Thnaks & Regards

Gangadhar

Former Member
0 Kudos

Hi Gangadhar,

The Corporate node and one subnode(Organization) under it should be created in the backend first. Please create those using the transaction 'GRPC_STR_CREATE' and assign the subnode to the Corporate. After you do this, those buttons should be enabled. Please let me know if you were able to resolve the issue.

Thanks & Regards,