Hi,

I have existing release strategy in purchase requistion.

Following are the characteristics linked to the class.

1) Doc type

2) Pur org

3) Pur group

4) Plant

5) Value

6) Acct assignment

7) PR creation date

Now i am adding another characteristics PR change date (Field ERDAT) to the above class.

If i am changing the older purchase requistions which was created earlier, it is not considering for release procedure. However new requistions that i have created today and changed are considered for purchase requistions.

Let me know what is that i need to do.