on 04-22-2009 8:21 AM
Experts,
I allocated to parts to one operation in router (CA02). One part has WM storage location second part has IM storage location. If I start a work order both parts are on the pick list, but system won´t create a transfer order for the WM part.
How can I set up the system that I get a transfer order for the WM part ?
Thanks in advance
Jörg
Dear,
Create the scheduling profile in OPKP with WM Request as X assign it to work scheduling view of header material. Define cycle in LPK1.
Please refer my reply from this thread,
http://help.sap.com/saphelp_470/helpdata/en/c6/f83e5a4afa11d182b90000e829fbfe/frameset.htm
Regards,
R.Brahmankar