Transfer req. in case of allocation IM / WM part per operation

Former Member
0 Kudos

Experts,

I allocated to parts to one operation in router (CA02). One part has WM storage location second part has IM storage location. If I start a work order both parts are on the pick list, but system won´t create a transfer order for the WM part.

How can I set up the system that I get a transfer order for the WM part ?

Thanks in advance

Jörg

Accepted Solutions (1)

Accepted Solutions (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Create the scheduling profile in OPKP with WM Request as X assign it to work scheduling view of header material. Define cycle in LPK1.

Please refer my reply from this thread,

http://help.sap.com/saphelp_470/helpdata/en/c6/f83e5a4afa11d182b90000e829fbfe/frameset.htm