Double line item getting genrated in production order apo while

Former Member
0 Kudos

Hello,

Double line item is getting generated for child item when planned order is converted into production order.

When conversion indicator has given to planned order it has getting converted into the production order.

But after some times if i check the production order then line item component has appeared two times.

I checked the ppm and bill of material found correct.

Please reply.

Regards,

Sunil

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Sunil,

Please check whether

1) Is there any integration models for the components duplicating for planned orders or production orders in R/3

2) Is there any faulty queues generated

3) Check the application logs whether any warning or error messages?

4) Try to manually convert one planned order interactively in foreground in /sapapo/rrp3 whether you are getting the same error or not like

5) Check the master data of bom, routing of the component under error in R/3.

Regards