on 04-21-2009 10:24 AM
dear all:
When I assign different materials to the wbs,the option of Procuremt Type sometime is "Reservation for network"and other may be "Reservation for wbs".Can you tell me what can control this?
It controls the account assignment of the materials...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I assign two materials to the same activity, one, there "Reservation for networ" can be choosed,
and the other no "Reservation for networ" can be choosed,there only "Reservation for WBS element" can be choosed.
I wonder what can control the options of Procuremt Type of the materials.
thank you!
Hi,
I dont think we can configure that. But we can control the options appearing.
The settings are in Material Master . Project System and Bill of Material.
Pls refer: Procurement Settings in
http://help.sap.com/saphelp_erp60_sp/helpdata/en/d7/b8853488601e33e10000009b38f83b/frameset.htm
Regards,
User | Count |
---|---|