cancel
Showing results for 
Search instead for 
Did you mean: 

Profit Center in PO

Former Member
0 Kudos

Dear Guru,

Need your help we introduce profit centre in our plant and some PO have deactivate Asset when i change the asset in PO system not pick the profit centre number against new asset.

All ready assign Profit center number to all Asset.

Regards

Aamir

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

did u change the screen settings w.r.t. account assignment categories?

if u havnt done so then please do so under menu path:

SPRO > IMG > MATERIAL MANAGEMENT > PURCHASING > ACCOUNT ASSIGNMENT > MAINTAIN ACCCOUNT ASSIGNMENT CATEGORIES.

regards

jash