mrp for phantom assembly

Dear Gurus

My main item is a phantom assembly the sales order comes for the phantom assembly only.I have got a multilevel bom for this phantom assembly .The bom of the phantom assembly contains the semifinished item. And the bom of the semifinished item contain raw materials.Now while running MRP I dont want any planned orders to be generated for phantom assembly the system should create planned order for semifinished item and purchase requisition for raw material.How can it be done.


Sandip Sarkar



Can you explain your business scenario, :

Why did you create the Finished Material as Phantom , If iot phantom how are you going to deliver it to Customer against the sale orders ?

Photom Material means it is virtual material i.e. literally speaking the item does not exists.


radhak mk