hi all,
i would like to create BOM which i will later use during BOM transfer.
however, some materials, i use for structuring the BOM only so i do not want it to be procured..
according to some i should use phantom item however the tickbox indicator is GRAYED OUT/UNEDITABLE in the item data of the BOM...
how do i do this? my main requirement is to be able to create multilevel bom where only lowest items are actually procured.. in the example, the level 3 items are procured while level 2 bom items are for structuring the BOM only so i would like to set it as phantom item.
EX: HOUSE1 - main BOM
ROOF - level 2 BOM
Nails - level 3 bom
Paint - level 3 bom
Tiles - level 3 bom
WALL- level 2 BOM
Hollow Blocks - level 3 bom
Cement - level 3 bom
Sand -level 3 bom
FLOOR- level 2 BOM
Steel Bar - level 3 bom
Cement - level 3 bom
Gravel - level 3 bom
Sand - level 3 bom
Hi Ramesh,
This is a material level setting. If you want only level 3 BOM items are to be procured then create level 1 and level 2 material as phantom assembly (set special procurement - 50 in MRP 2 view and procurement type as no procurement) in material master and then create your BOM as mentioned. During BOM transfer in CN33 select the check box for multilevel and then your purpose will be solved.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
in Mat Master MPR2 view set "Special procurement" as 50.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.