on 04-20-2009 11:15 AM
Hi
In transaction like VA02/VA03 or IW32/IW33 or MM02/MM03 - we can track /see the history of who has created and when , what , who did the changes.
But in the Project builder - we can see only who& when created the Project and who & when was the last changes in the Project definition / WBS element / Network and not for Activity or Activity Element.
Seems this is SAP standard.
To keep the history of the changes - Is there any customization / enhancement to be done ? Is the enhancement can be done with BADI / BAPI / need to do the coding ?
if yes in which way can able to achieve this .
kindly reply on this query.
Regards
PP
use transaction CN60 for tracking changes. you have to activate change cocuments in proj profile for that
Sarang
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
in Transaction OPSA Project Profile in Control Tab Tick the indicator Change Documents.
and then check it in Transaction CN60
Regards,
Nitin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Based on the activation in the Project and network profile , history of the changes is reflecting in CN60.
But for example when the material qty is changed or material is been deleted or new material added - these changes not reflecting in CN60 eventhough - Material Status changed doc is been enabled in OPUV.
Is the changes/deletion/new addition for the material in the Project builder will reflect or only till network level is possible? is there any other config changes to be done or enhancement is required.
do help on this.
Regards
Pavan