on 04-20-2009 8:20 AM
Hi All,
Please note that we are facing a problem in our production system. For a retail replenishment purchase order the sales order has been created in core system and production allocation(PA) also completed for that item. But even after that also the confirm schedule line(CSL) has NOT been created.
Because of this delivery is not created.
Please let me know the reason why the CSL not genereated even after PA completed.
Thanks in advance.
Regards,
Chandru
Hi Chandru,
Take a look at the MD04 (ATP check) and MMBE (stock check) and check if there is enough quantity for the CSL. If you are using the same sales order try to update it. Delete the item and put it again in the Sales Order.
Hope this helps you.
Regards,
John
SD Consultant.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
CHANDRAMOHAN NATARAJAN ,
1. Please check "Carry out control for Availability Check" - OVZ9
For you sales order combination
Check whether you have activated "Check without RLT" then deactivate it and try
2. Check "Define Procedure for Each Schedule line category" - Tcode. OVZ8
3. IMG --> SD --> BF --> Availability Check --> Availability Check against product allocation -->
"Process Flow for Each Schedule line category"
Regards
Sathya
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
CSL is only confirms whn stock is available in un-ristricted use ,so check a stock for that item
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.