Dear all,

My activity is to do survey for which i need 2engg. and 1 supervisor for 2days.now how can i assign this? If this is to be done thru activity element then how? To main activity we will assign 2engg. then we will add one activity element to it , IS it so ?

Regards,

Former Member
Former Member replied

Go to Capacities tab page and define different capacity category. You can set up different formula, capacity for eacxh of them (example - create capacity such as Engg, Labour etc)

Define different activity types for each category and define a rate for them against Cctr in KP26.

In costing tab of Work center in Activities overview select the activity type from drop down

Thanks