Hi
This can be achieved easily through careful customization
In your schedule line category determination in sales orders in t code VOV6 you need to maintain one automatic schedule line category and manual schedule line category
Suppose if the automatic say is CP and manual is say ZCP
In CP turnoff Availablity check and in ZCP turn on Availablity check
Now sales order created with the schedule line category CP without an Availablity check
Now when you are going to do Availablity check manually change the schedule line category from CP to ZCP and then do it
This will fulfill your requirement
As on when changing the spro settings is not a ideal option and changing the schedule line controls manually in sales order should be of no problem
Note your ZCP should be exactly the copy of CP in all aspects and should be that same as CP but for Availablity check indicator ticking
Regards
Raja
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Paresh
the buisness need is based on the requirement and we need to service to the customer who is running out of stock
thanks for help
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
Can you please explain ,,,,,,,why business dont want to carry out the Availability during order creation and only want to do check at certain point later.
I think by standard functionality it wont be possible.
regards,
Paresh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear fnds,
As per my Under standing ,Define one Order type(ZOR),for this you should not assign any Schedule line category ..You can Create the Sales order and Save it
When you want to Create the Sales order (NOR)with Availability Check...copy ZOR to NOR..
Maintain all Setting Which are Link to (Requirment Type &Checking Rule) NOR order....
Revert back if you need more clarity.
Regards
raj.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.