on 04-06-2006 7:35 AM
Hi,
I am configuring CProject 3.1 to activate the single-object controlling so that an internal order can be created after replicating a project from CProject to R3. It works now.
But the problem is, this internal order number is suppose to be identical to the project number. How can it be done? I can't find BADi for this purpose. Dose anyone have any suggestion?
Hi Kitty,
did you checked out the Badis DPR_FIN*
e.g. the DPR_FIN_GECCO_CALC
I hope this will help.
Regards
Björn
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Kitty,
Can you please give the details why i get the
error which i have mentioned in the "Accounting
Integration Error" message.
If you have any document pls share with me
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
We have the cProjects 3.1 system seperately
and ECC5 System seperately. I have connected
through the RFC. There is no messages in SMQ1
Can you see the message given by me
with subject
" cProjects & R/3 Accounting Integration "Company Code not found" "
I have elabroated the details there.
Regards,
1. ECC5 should have plugin installed
2. where is the om maintained? the integration use org number not abbreviation to find the corresponding org. the org number must be identical!
3. in the project of CProjects, you should maintain "organization unit" in "additional data" tag
good luck
Regards,