CTM aggregated planning

Former Member
0 Kudos

I have been working on CTM aggregation. We have created the master data for the CTM aggregation. The issue that we are facing is when we create the replenishment plan then it is created at the header level but when we want to disaggregate the replenishment plan to the sub level using the SNP disaggregation, we want it to consider the priorities at the sub level that have been maintained in the CTM profile when creating the replenishment at the sub level.

Could you plz let me know how this can be achieved.

Thanks

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

Can I know what field selectiions you have choosen in Aggregation tab in CTM profile.

Planning level

Order group. etc

Are you maintaining the order group?

Do let me know.

Regards

KRN