The confirmation of Activity

Former Member
0 Kudos

The user need to use CN25 to process the confirmation of activity A.

The confirmation is below:

Activity Actual Start Actual finish Confirmation: Degree of processing

For the 1st time. A 20090301 20090307 30

For the 2nd time. A 20090309 20090312 20

For the 3rd time. A 20090315 20090320 10

For the 4th time. A 20090322 20090329 100

For the 5th time. A 20090315 20090320 -10 (cancel 3)

Now the status of Activity "A" still is "CNF".

because the confirmaiton have some errors.

how to customize to avoid to appear this errors.

Please explain me all the steps to be required.

Thanks in advance!

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

I think you have done some kind of mistake while doing cancellation also...

If we properly cancel all the confirmations for an activity then it will not be having CNF status.

Regards.

Answers (0)