on 04-17-2009 10:18 AM
Hi,
When I enter working time of tasks through IDES Potal screen in Demo system (DL3 - long-term),
entry screen for following attributes is not displayed.
- Actual Start Date
- Actual End Date
- Remain Work (if it was set in IMG configuration)
- Degree of Processing in Percent
- Comment
If you have same experience, let me know reason and solutons.
Thanks
regards,
JaeMan
Hi Jae
We had observed that Degree of Processing in Percentange is not apearing automatically.
Others as far as i remember are appearing after entering the times in timesheet.
Regards
Prasad