on 04-17-2009 8:22 AM
hi everybody
my ps scenario is running good but i have an issue regarding the display report in project planning board
first of all i will explain my ps scenario
am involved in a service project which contains for example two level of wbse and say i have two wbse in the second level and each wbs in the second level the cost is showing at the int activity level which is fair enough.
and two milestones are added to each 2nd level wbs element respectively(milestone assigned to the wbs element respectively). following is the display in project planning board before adding milestone in the sales order as follows
project plan cost
pro def 80000
wbs1 80000
wbs2 45000
activity1 25000
activity2 20000
wbs2 35000
activity1 25000
activity2 10000
now after saving the sale order with milestone and say the total bill is say 100000 then in the project planning board the following display i see which is shown as follows
project plan cost
pro def 20000-
wbs1 20000-
wbs2 45000
activity1 25000
activity2 20000
wbs2 35000
activity1 25000
activity2 10000
the project planning cost of project def and wbs1 level changes to 20000- i dont know y? but according to logic it should still so 80000 as we planned
now after i billed the first milestone bill say the bill is of 50000 then the following thing happens in the actual cost column shown as follows
project plan cost actual cost
pro def 20000- 50000-
wbs1 20000- 50000-
wbs2 45000
activity1 25000
activity2 20000
wbs2 35000
activity1 25000
activity2 10000
now when i add actual cost in the internal activity through cats the following display comes in the project planning board shown as follows
project plan cost actual cost
pro def 20000- 48000-
wbs1 20000- 48000-
wbs2 45000 2000
activity1 25000 1000
activity2 20000 1000
wbs2 35000
activity1 25000
activity2 10000
but in the actual cost level it must show 2000 which is not showing and even after i generate revenue the actual revenue is also not showing in the revenue column
am new in project system so can any body help me how can i repair my development server and even i referred the ides to check what setting i missed. but still it didn't help me so am really looking forward for your help if i missed any setting. looking forward for ur help
regards
subhro
Try CJEN and then see the result again
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
thanx for ur response but Frankly speaking i need to know one thing like in the project planing board u have seen that before entering the milestone the project planning cost was okay (80000) but when enter the milestone in the sales order the figure in the project planning board changes to 20000- as the total bill is 100000. some where its getting calculated automatically which i don't want. so mu issue is i need the plan project cost to show 80000 not 20000-.
i guess some setting is there which i missed. looking forward for ur reply
regards
subhrangshu