Dear all,

While working we have found that for our project all the scheduling has been carried out in pjt. planning board and finish dates have come . But when we try to look in project definition , basic data tab , dates field , only start date is coming , finish date field is empty . why ?

Regards,

Accepted Solutions (1)

Accepted Solutions (1)

virendra_pal
Active Contributor
0 Kudos

in planning board the finish dates (actual dates) are based on confirmation

you need to extrpolate them to the WBS from planning board

once this is done or all the WBS elements int he project the extrapolation will also set the finish date for the project

Former Member
0 Kudos

dear Pal sir,

How can we extrpolate the dated to WBS ?

Regards,

Former Member
0 Kudos

In Project Planning Board> Edit Menu>Reconcile Dates---> Extrapolate Dates