on 04-05-2006 5:33 PM
Hi,
Hi,
I have a ODS to ODS data mart and the load is by process chain. A have the following chain : Start->LOAD DATA (ODS1) -> activate ODS object Data -> Update ODS Object Data (Further Update). This update execute an delta infopackage which has two ODS like data targets to update (ODS2 and ODS3).
The process chain is executed correctly, but the ODS2 and ODS3 requests are not active, request for reporting is not available.
What happens?
I need to make another thing?
Thanks
Victoria
You need to add 2 separate "Activate ODS object Data " processes for the other two ODS Object i.e. for ODS2 ODS3
Same thing you can do in the Manage screen of the two ODS Object.
Regards,
Ashish
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Victoria,
You will have to add another process (activate ODS object Data ) to activate the ODS2 and ODS3 data, after the Update ODS Object Data (Further Update) process.
Hope this helps...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
84 | |
24 | |
12 | |
9 | |
7 | |
6 | |
5 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.