Hi I am working in co-product scenario.As per my scenario any two materials can be produced as co-products.Eg. I can produce material A and B today in one production order.Latr i can produce A and C.

Here req. will be entered for individual materials(A,B or C). Is it any setting is there for converting planned orders of A and B into one production order or Is it any setting is there for converting planned orders of A and C into one production order.?

Accepted Solutions (1)

Accepted Solutions (1)

former_member196398
Active Contributor
0 Kudos

Velu,

Please go through this Link my explaination on [Co-Product and Bi-Product Scenario|;

Regards,

Prasobh

former_member189817
Active Contributor
0 Kudos

Hi Prasobh ,

Thanks for your reply.I am clear about co-product and By-Product.Here my requirment is MRP is generating separate planned order for main as well as co-product since requirments are craeted separately for both.I want to convert them into one production ordr.Because Rawmaterials and operation cost are apportioned by them using equivalence numbers.