on 04-16-2009 6:40 AM
Hi Folks
Does CNE5 store the progress results anywhere in the database or it scraps the progress results once the report is run and exited?
Please share your expert opinion. I have to use the progress results of CNE5 in a custom report.
Thanks & Regards
Waz
Use RPSQT table...input ur Obj number..then use value type P1 for Planned EV and P2 for actual EV, then use value category which u made for POCagg..POCnonagg..etc..to find the value of POC