Massive change to Prch Group on Mat Mstr - How to update requisitions

Former Member
0 Kudos

We have made a massive change to the Purch organization:

Vendors for materials have changed

Materials are aligned under new buyers.

Material Masters have been updated with new Purch codes

How can we delete all requisitions that are not converted to PO's so MRP can regenerate the requirement and pick up the new Purchasing codes??

Thank you

Althea

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Try changing the planning mode = 3 (Delete and Recreate Planning Data) in the MRP control parameter.

Former Member
0 Kudos

Planning Mode 3 - is our answer

We tested the settings with MD02; are testing the MRP run in QA system and will update production this weekend.

Thank

althea

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Althea,

The best what you can do is to create LSMW for deleting PR's.

Best Regards,

Rahul.

Former Member
0 Kudos

We do not use LSMW, yet.

Any other ideas?