on 04-15-2009 3:17 PM
Hi
I have created a daily work schedule, period work schedule and work schedule rule and generated work shceudle from 012009 to 122011.
when the user in infotype 2001 tries to create holiday for 04092009 04092009 , it gives a message
Counting class of period work schedule 08/PS79 not available on 04.09.2009.
Can any body guide me what can be the cause of the problem, Am I missing something with configuration.
thanks in advance
Anup
Hi Anup,
Please check V_T551C and check if the PWS is assigned with the correct counting class and its validity.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Have you assign the counting classes to period period work schedul in the V_T551C.
Here 08 - Daily/PWS grouping
PS79- Period work schedule.
Regards
Devi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Have you assign the counting classes to period period work schedul.If assign in the table V_T551C.
Thanks
KB
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.