WBS element not picking in network during material assignment

Former Member
0 Kudos

When I assign requirement quantity in network using CN22 it does not pick wbs element and as a result PR during MRP run is created without a account assignment. could you please let me know the reason for the same.

regards

Raj

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

check the material master...tab MRP4 field Individual/coll. Enter a "1" and try again...