on 04-15-2009 1:31 PM
When I assign requirement quantity in network using CN22 it does not pick wbs element and as a result PR during MRP run is created without a account assignment. could you please let me know the reason for the same.
regards
Raj
Hi,
check the material master...tab MRP4 field Individual/coll. Enter a "1" and try again...
Kind regards
Jan