Hi,

we want to maintain all plan data in different version than '0'. how to maintain new CO version.

Thanks!

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

thanks!

Former Member
0 Kudos

Hi Harsh,

Please ask your CO guy in your project.

Muzamil

Former Member
0 Kudos

SPRO> Project System>Costs--->Create CO Versions

Former Member
0 Kudos

Hi,

i know that path but i don't understand that screen.

Former Member
0 Kudos

Have u seen the help available in SAP menu ( besides '' Create CO versions'')?

luis_rocha2
Explorer
0 Kudos

Hi Saxena,

just copy version 0 to a new version and make sure "plan" is selected.

Then select that new version and select "settings for each fiscal year" under controlling area.

Enter the fiscal year you want to start planning and check the exchange rate type you want to use for conversions...

save and this should be able to get you started...obviously, checking the documentation on all other options is the next step.

best regards,

Luis