Communication error SRM<->R3

Former Member
0 Kudos

Hi experts,

I would need an advice what might be the issue if we do not get back the follow on document creation info from R3 to SRM. In SRM we see that a follow on doc was created, but the information of PR or PO nr is on the web missing. When we check bbp_pd, there is only the information that a PR with xxx number was created, but again: PO nr. is missing. The item status is In process, however the PR or PO was created and there was any error message found. So everything seems to be ok, except that we do not get the document number information back from the backend. This issue causes that no GR can be generated, as the PO number is in SRM missing. Workaround might be GR creation in backend, not via SRM. By the way: RFC connection works fine. Any idea where to look?

thank you very much for all hints. katarina

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Check the following batch reports are scheduled and running properly every two minutes.

1) BBP_GET_STATUS_2

2) CLEAN_REQREQ_UP.

Regards

Anirban

Answers (2)

Answers (2)

Former Member
0 Kudos

Issue occurred while implementing support packs u2013 see OSS note 1233774,

WF for SC to be restarted via swpr

Steps: SC needs to be put in error via the transaction se 38 -> BBP_ALERT_SB_NOTTRANSFERRED -> !!!! timestamp to be changed beforehand. Once the SC item is in Error in transmission, it can be transferred to the backend via se37 -> fm.: bbp_pd_sc_transfer. In case the information of follow on document creation (PR reference, PO reference) is not visible in SRM (on the web) -> check RFC User authorizations

peter_novoth
Employee
Employee
0 Kudos

Hi Katarina,

please check the report Z_SC_STATUS_CHECK_3 as in the note 729967 described.

Regards,

Peter