Cost Centre Assignment

HI all,

I am seeing 2 options for assigning CC

1) We can do it thru PO13

2) We can do it by directly going to " Cost Distribution" which is at the top of the screen.

Is there any difference B/w the 2?

Former Member
replied

Check with slavis reply

yes there is difference

if u go through the PO13 or PP01 this will be at position level (OM LEVEL)

if it is thru 0027 it will be from PERNR LEVEL (PA LEVEL)

as both are same in nature

the configuraion and master data maintainence will change