on 04-15-2009 7:41 AM
HI all,
I am seeing 2 options for assigning CC
1) We can do it thru PO13
2) We can do it by directly going to " Cost Distribution" which is at the top of the screen.
Is there any difference B/w the 2?
For the 2nd one, which screen you are looking at
Regards
VM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
The cost center u assign in OM thru PO13 or IT1008 - Account assignment becomes the master cost center for the employee hired in that position. It will appear in IT0001 infotype for the employee in PA if integration is active.
IT0027 - Cost distribution is available where in you can assign other cost centers to which the cost of the employee is distributed based on percentage.
Hope this helps.
Regards,
Shreyasi.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Cost Centre Can be assigned at positon level in PO13 , PP01 and also at Pernr level thru IT0027
u can go ahead
kidnly check
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.