Transferring cProject structure to PS

Former Member
0 Kudos

Hello,

When we transfer cProjects structure to PS structure using standard integration, it is observed that the structure created in PS is in reversed order as compared to cProjects structure(i.e WBS sequence is reversed). Please advise to resolve.

Regards,

Milind Dumbre

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

This message was moderated.

Answers (1)

Answers (1)

Former Member
0 Kudos

Hello!

When transfering cProject structures to PS, the left to right sequence of the project elements is not adhered to during the transfer. SAP already told in OSS note 954151 that they will not change the programming. As a result, the PS structure is correct at level definition, but the sort is reversed.

We have to live with this.

Matthias

Former Member
0 Kudos

Thanks Matthias and Nishit,

Your answers were helpful.

Regards,

Milind Dumbre