on 04-14-2009 6:34 AM
Hi All,
To schedule a global planning sequence in time , usually we use the program 'UPC_BUNDLE_EXECUTE ' and define a job which will execute the program. Is there something similiar program in Integrated planning which can trigger the planning sequence. Is there a way around that we can use the same program to work . I have already seen the sap help
http://help.sap.com/erp2005_ehp_03/helpdata/EN/43/0c033316cd2bc4e10000000a114cbd/frameset.htm.
Thanks in advance
You can create a process chain and in that uou can define the process type 'Planning Sequence' . That process chain can be scheduled and will run in background.
You can also use ABAP program RSPLS_PLSEQ_EXECUTE.
Edited by: Deepti Maru on Apr 14, 2009 10:43 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
please note that RSPLS_PLSEQ_EXECUTE is designed as a debugging tool and should be used like that. In your production environment you should use the process chain approach mentioned above [http://help.sap.com/saphelp_nw70/helpdata/EN/45/946677f8fb0cf2e10000000a114a6b/frameset.htm].
Regards Matthias Nutt
SAP Consulting Switzerland