on 04-14-2009 12:40 AM
Hi all,
I'm having trouble setting planning strategy 50, I've done the following:
Strategy group 50 on the MRP screen
Consumption mode = 1, and Backward days = 100
Item category group = NORM on the Sales Organization screen
A BOM is set for the finished product.
components settings:
Set MRP type = P1
the Individual/coll. indicator = 2 (for a make-to-stock procurement of components in a make-to-order environment).
Then,
Entered Planned Independet requirements (VSE) at 100 pieces for three months.
Entered Sales order for 90 pieces for the second month, (req, type KVE)
I should see a consumption on the stock/requirements list of 90 pieces for the first planned independent requirement, it should display a qty of -10 on the received/required quantity column, but it's not happening. What is missing?
I'll appreciate your kind help
Regards
TR
Edited by: tonatiuh ramirez on Apr 15, 2009 5:42 PM
Hi TR,
I applied the setting described by you:
material
- MRP type: P1
- Strategy group: 50
- Consumption mode: 1
- Backward consumption: 100 days
- Item category: NORM
- Individual/collective indicator: 2
PIR:
- PIR entered for three months, 100 pcs for each
SO:
- 90 pcs
IndReq qty has been reduced from 100 pcs to 10 pcs just as in the example in SAP online help....
But the requirement type of my SO item is "041" (V_TVEPZ_V).
Requirement type "KVE" mentioned by you does not exist in our (standard) system ...please try to use "041" and test whether it works or not...
Regards,
Csaba
Edited by: Csaba Szommer on Apr 15, 2009 7:38 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.