on 04-13-2009 9:00 PM
Client receives funding from government, which has strict rules.
One of the rules is that the expenses should spent exactly as funded.
For example funding for:
Travel expenses: 10.000
Consulting: 15.000
Wages: 8.000
WBS is planned for each cost element item and transfer to the budget.
However, the availability control will not check on the expense level but on the total budget.
Is there a way to do the availability control on the expense level instead of on the total budget level ?
HI myron,
Nitin is Absolutely right, you need to assigned budget at top level and you have activated budget availability check via define budget profile and tolerance limit as well
in that case system will check budget when you will do any business transaction with the account assignment of concern wbs.
Regards,
Sanjeev
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Myron
What Nitin suggested is appropriate & easy. That'll solve your issue.
Create individual WBSE for allotted fund for a particular job.
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Here work around can be, if you create one level one WBS and under it you create three lelve 2 WBS
lik as Travel expenses: 10.000
Consulting: 15.000
Wages: 8.000
and assign the budget exactly eaula to expense. and total of expense ile 33.000 assign to top WBS.
Regards
Nitin P.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.