on 04-13-2009 10:17 AM
Hi Gurus,
I have a scenario where the main item required to execute the Project has a lead time of more than one year. The project is executed in 4-5 months period hence it is decided only at the start of the fiscal year. In such cases, the project will be created only after the fiscal year starts or just before that and the budget will be allocated only after the fiscal year started whereas the PO for material has to take place long before so that the item is received on time to execute the project. How to handle such cases ?
Thanks
Vinodh.
Closed
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
What will happen if I maintain the "No Stock" indicator and raise PRs through activities ?
thanks in advance.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.