I am running SNP - Heuristics in Monthly / Weely Bucket. Unlikely, system is generating a Planned Orders in Middle of a Bucket. Kindly give the Inputs for planned orders to be generated on first day of bucket.
Note: I also worked with Period Factor in PPM & Location Product, system is generating planned orders in middle of a bucket
Regards
Guru
Hi Guru,
1) Please check the maximum earliness & lateness of a receipt under Pegging in Demand tab of APO material master is defined.
2) In SNP2 tab, check the period split whether the data is blank. If it is 2, the planning data will get disagregated and released from middle of bucket.
Regards
R. Senthil Mareeswaran.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
11 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.