Hi,
What are the configuration settings i need to maintaining project costs and revenues ?
we have 4 types of projects: customer, rnd, maintenance, academic.
we are giving all costs and revenues only on top wbse.
thanks!
hi
you have to set the settings under
Project System -- Costs -- Automatic and Periodic Allocations -- Settlement ---Settlement Profile
Create Allocation Structure
Create Source Structure
Define PA Transfer Structures
Create Settlement Profile
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
thanks!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Harh,
Also refer below link for "Peroid End Closing Activity for Customer Project" which will be usefull for settlement.
http://help.sap.com/saphelp_46C/helpdata/EN/51/5828e4a44c11d189bf0000e829fbbd/frameset.htm
Regards,
Sandeep
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Harsh,
Normally Above conf setting is done by FICO consultant.Get it done through them.
From PS point of view you need to assign Settlement profile to Project Profile.
In Project Profile, Controlling Tab, you can see Peroid End Closing sub secreen there you have to assign settlement profile.
As you mention various project types, for that you have to create seperate project profile & in each project profile you have to assign settlement profile.
Hope this is useful to you.
Regards,
Sandeep
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.