on 04-11-2009 11:09 AM
LSMW for ORG assignment done via PP02, but while trying to run RHINTE30, it give the following error
Number of personnel nos. selected : 0
offcourse I had enter the personnel number
cai it be a problem due to global employeement??
we have activated the global emloyment switch, is the problem becuase of the same?
Try RHINTECHECK once thru SE38
before that make sure the master data of that pernr from OM and PA are right
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
checked,
checked the switches, switch from OM to PA is active, defults the PA-PSA from OM to PA as required
check using RHINTECHECK = no able to select the personnel number
also
can pid and pernr be used in rhinte30, for I am having a doubt that RHINTE30 is not working because pid exsists??
not able to understand
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.