PRICE CHANGE BASED ON DELIVERY DATE

amit_chavre
Explorer
0 Kudos

Hi,

I want to know that how a price date category (2- delivery date) in Infor Record controls the material price change based on delivery date ? That means I've created PO specifying price for a material & on particular delivery date price change occurs.How to map it?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

In the info record, you have specified that the price determination process is to be carried out with the conditions that are valid on the delivery date (pricing date category 2). Furthermore, you have created two validity periods (from 04. 01.2009 until 04. 31.2009 and from 05. 01.2009 until 12. 31.2009), each with different conditions.

You create a purchase order with the delivery date 05.05.2009. The pricing date category from the info record is adopted. In the course of the price determination process, the info record conditions from the validity period 05. 01.2009 until 12. 31.2009 are then adopted.

If you wish to adopt the info record conditions from the first validity period in the purchase order, you must change the pricing date category in the PO to blank and carry out a new price determination process.

Hope this helps.

Regards,

Zafar.