I have assigned two work centers with capacity category machine and labor in different activities of my project.
Now when I am going to the capacity overview the whole histogram or the bar is shown in green. This means there is no overload i think.
When I am going to the capacity load list it is giving message
"No capacity requirements were found in the evaluation period"
I have tried changing the evaluation period in spro but still not giving the load
why is this happening?
Plz help
Activate Cap.Requirement and then do scheduling....then check the capacity histogram....