Plan driven procurement

Former Member
0 Kudos

Hi Experts,

I need to configure Plan driven procurement for my project.Can any please provide me what are the settings to be carried out in srm as well as R/3 system.

Thanks in Advance,

Bhaskar.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Please ensure that following Settings are maintained in both SRM and R/3 systems.

These are Plan Driven Procurement - Prerequisites

SRM system settings

-> perform all steps for direct material

-> set up entry channel for external requirements

-> assing an RFC user for this entry channel

-> assign your local purchasing group as responsible for this channel

-> set up sourcing configuration

R/3 Backend settings

-> maintain tables V_T160EX and V_T160PR

-> make sure to have a RFC connection to the EBP system, with the same RFC user as in the entry channel (with SAP_ALL and SAP_NEW Profiles)

-> schedule report BBP_EXTREQ_TRANSFER to transfer the requisitions to EBP

After customizing the direct material, there are additional steps necessary:

-> Using an entry channel, the requisitions are transferred into EBP. This channel must have at least one

entry user.

-> Corresponding to this entry user, you have to set up a RFC connection from back end to EBP by using

this special RFC user.

-> To get the requisitions in the work list for purchase orders, or in sourcing, there is a local purchasing

group required with the responsibility for the entry channel and the product category of the back-end

requisitions.

-> View V_T160EX in the R/3 back end determines which material groups and purchasing groups are

grouped into a profile. View V_T160PR determines which profile targets to which RFC connection.

Thanks,

Koushik.

Answers (0)