Hi Experts,
I need to configure Plan driven procurement for my project.Can any please provide me what are the settings to be carried out in srm as well as R/3 system.
Thanks in Advance,
Bhaskar.
Hi,
Please ensure that following Settings are maintained in both SRM and R/3 systems.
These are Plan Driven Procurement - Prerequisites
SRM system settings
-> perform all steps for direct material
-> set up entry channel for external requirements
-> assing an RFC user for this entry channel
-> assign your local purchasing group as responsible for this channel
-> set up sourcing configuration
R/3 Backend settings
-> maintain tables V_T160EX and V_T160PR
-> make sure to have a RFC connection to the EBP system, with the same RFC user as in the entry channel (with SAP_ALL and SAP_NEW Profiles)
-> schedule report BBP_EXTREQ_TRANSFER to transfer the requisitions to EBP
After customizing the direct material, there are additional steps necessary:
-> Using an entry channel, the requisitions are transferred into EBP. This channel must have at least one
entry user.
-> Corresponding to this entry user, you have to set up a RFC connection from back end to EBP by using
this special RFC user.
-> To get the requisitions in the work list for purchase orders, or in sourcing, there is a local purchasing
group required with the responsibility for the entry channel and the product category of the back-end
requisitions.
-> View V_T160EX in the R/3 back end determines which material groups and purchasing groups are
grouped into a profile. View V_T160PR determines which profile targets to which RFC connection.
Thanks,
Koushik.