How can I limite the creation of MRP element Pldord under 8000 LBS

Former Member
0 Kudos

Hi all,

I do not want the mrp to create a pldord when the pldord qty to be created is under 8000LBS.

Is there a way to do this in MM02 - in view MRP1,2,3 or 4 ?

Regards!

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

If qty greater than 8000 lbs I want the system to create the plan order

If qty less than or equal to 8000 lbs I dont wnat the system to create the plan order.

csaba_szommer
Active Contributor
0 Kudos

Hi,

You can't achieve this in SAP as per my best knowledge, since the system won't allow material shortage during (automatic) planning. There are several lot sizing procedures but I think none of them covers your requirement.

http://help.sap.com/erp2005_ehp_04/helpdata/EN/fe/819b9f643b11d3b4e40004ac160649/frameset.htm

What Priyanka P. suggested makes no sense because using external procurement key won't solve this at all - you will get procurement proposal: either PldOrd or PurReq (or something else) based on your selection parameters for MRP run.

Regards,

Csaba

Answers (1)

Answers (1)

former_member581212
Active Contributor
0 Kudos

hi,

If you don't want Planned order to be created, then use the procurement type indicator only for External in the MRP 2 view of MMR ie material master record MM01/02/03...

Via this system will not generated the planned order any time...

and material will not be procured internally...

You can't limit for qty....

Regards

Priyanka.P