How can I limite the creation of MRP element Pldord under 8000 LBS

Hi all,

I do not want the mrp to create a pldord when the pldord qty to be created is under 8000LBS.

Is there a way to do this in MM02 - in view MRP1,2,3 or 4 ?

Regards!

Former Member
Former Member replied

Hi,

You can't achieve this in SAP as per my best knowledge, since the system won't allow material shortage during (automatic) planning. There are several lot sizing procedures but I think none of them covers your requirement.

http://help.sap.com/erp2005_ehp_04/helpdata/EN/fe/819b9f643b11d3b4e40004ac160649/frameset.htm

What Priyanka P. suggested makes no sense because using external procurement key won't solve this at all - you will get procurement proposal: either PldOrd or PurReq (or something else) based on your selection parameters for MRP run.

Regards,

Csaba