on 04-09-2009 1:45 PM
Dear All,
I am extending the Material from one Plant (P001) to another Plant (P002) under same company code through MM01.
I have changed the delivering Plant as P002 while extending. But, when I check in the original material master (P001) there also plant is getting changed to P002 ?
But, I want for Plant P001 - Delivering plant should be P001
And, for P002 plant - Delivering plant should be P002.
How will I achieve this?
Thanks & Regards,
Ram
Hi,ramu,
As we know a delivering plant in MM field is in sales org1 view so , it means this field is dependent on only sales org lavel data not on plant lavel data
That is the reason system changing delivering plant in MM
regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Closing the issue
Thank you all for ur valuable suggestions...
Regards,
Ram
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
Go to MM02 and put the material no and only sales org data 1 view and in the organizational data give P001
In the sales org data 1 view maintain delivering plant as P001
For the second plant also the same thing
Go to MM02 and put the material no and only sales org data 1 view and in the organizational data give P002
In the sales org data 1 view maintain delivering plant as P002
Regards
Raja
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Go to material master MM02, input the material code and click on "Select views". From the displayed list, block "Sales: Sales Org. Data 1" and click on "Organisational levels". There key in P001 and its sales area and execute. Check which plant you have assigned there against the field "Delivering Plant".
Similarly follow the above steps for other plant.
thanks
G. Lakshmipathi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
In Enterprise structure settings have you maintained both P001 and P002 as delivering plants in the assignment of img-Enterprise structure -
Propably here delivering plant assignment for P001 might be missing in your case
Regards
Raja
Sorry Ramu
There is a basic error in the first suggestion By me
It has to be done in MM01 and not in MM02 (as suggested by me earlier)
In MM01 you are creating one more
But in MM02 we are changing the existing one
That might be the problem
Do this
I beleive that you have already created the material in plant P001
In this in sales org data 1 tab the delivering plant is P001
Now you are extending the material to plant P002
Go to MM01 and put the same material no and select all viewsand in the organizational data give plant as P002
You will get a message that the material is already created and extended to the P002 plant
Then all the views (apart from the basic tabs) or exept the basic tabs will open and all the data pertaining to the plant 1001 would have been copied which you need to change
In that select delivering plant in sales org data 1 tab and change it 1003 (it should happen)
Hope this helps
Dear Ramnathan Raja,
Thank you for ur replies,
First I have done in the same manner (as per ur latest reply ), it has not happend then I posted the query in SDN, then I have followed as per ur first reply (through MM02) but, unfortunately both are not giving the results as I required i.e
For Plant P001 - Delivering plant should be P001
And, for P002 plant - Delivering plant should be P002.
While extending the material through MM01, system is giving a message as below:
"The material already exists and will be extended
Message no. M3364
Diagnosis
The material master record has already been maintained by another department for other views and/or for other organizational units. It will now be extended to include data for additional views and/or additional organizational units."
Plz guide me.
Thanks & Regards,
RAM
Hi Ramu
As per my understanding the system response is very correct and we are only misinterpretinthe same
Your sales org is S001
Your DC is 1
You have 2 plants P001 and P002
Say a material PEN you have already created for org structure sales org S001,DC 1, and plant P001
This is already done
Now you want to extend the material to plant P002
Steps to follow
1.In t code MM01 input the material as PEN then the same material type and industry sector
2.Select views (you will select whatever views that you want) and enter
3.System will ask you fill up org data like plant, storage loc,sales org,DC, etc
4.Here you have to give plant as P002 and your new storage loc,sales org S001,DC as 1 and enter
Now the system will throw a message that the material is already created and extended for such and such plant
After this exept the Basic data 1 and 2 every thing will open and you will find the values are already there (what is created for plant P001) which is modifiable
Values are already copied from the earlier creation which you need to change now which is suitable for this plant P002
In this sales org data 1 tab you can change the delivering plant to P002 which was already copied as P001
This should solve your issue (I have checked this too)
Regards
Raja
Yes Ramu
For me too same thing is happening
For a sales org and distribution channel (this combination is called as distribution chain) it looks like there can be single delivering plant and the last entry takes actual control
For example if there are 10 plants say 0001 to 0010 and you maintain your material in all 10 plants if there is a single sales org say 1000 and distribution channel say 10 then we can define or the system takes out of the 10 only one plant as a delivering plant for all the 10 stock maintaining plants
To define all the 10 plants as delivering plants (to have a selection choice) we need to maintain all these 10 plants has to be maintained as 10 entries in imgenterprise structuassignment-sales og +DC assignment to plant
That means delivering plant for a single Sales org +DC can be only one and cannot be multiple in the material master data
Hope i am clear
Regards
Raja
Yes you need to go with 2 sales orgs S001 and S002 and distribution channel as 01
Plants P001 and P002
First create the material
MM01 t code input organizational data as Plant as P001 and (sales org + dc) as S001 and 01 and give the delivering plant as P001
Step 2 Again in MM01 extend the material to plant P002 and (sales org + dc) as S001 and 01 and give the delivering plant as P001
Step 3 Again in MM01 extend the material to plant P001 and (sales org + dc) as S002 and 01 and give the delivering plant as P002
Step 4 Again in MM01 extend the material to plant P002 and (sales org + dc) as S002 and 01 and give the delivering plant as P002
There will be 4 material master records
In imgenterprise structure-assignmnet
In that i think two assignments should be sufficient That is
S001 + 01 the delivering plant is P001
S002 + 01 the delivering plant is P002
So whenever the combination S001 and 01 falls the delivering plant will be P001 and
whenever the combination S002 and 01 falls the delivering plant will be P002
This should be the best for your requirement
Regards
Raja
User | Count |
---|---|
90 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.