. Can it be configured in such a way that the external requisitions can also be taken into account while MRP runs in consumption-based planning if VB is selected as MRP type
Hi,
Use MRP type - V1 Manual reord.point w. ext.reqs
In OMDQ you can check which external requisitions are considered for this MRP type, you can customize a new one for your specific need.
Hope the above clarifies your query.
Regards,
Vivek