VB planning

Former Member
0 Kudos

. Can it be configured in such a way that the external requisitions can also be taken into account while MRP runs in consumption-based planning if VB is selected as MRP type

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Use MRP type - V1 Manual reord.point w. ext.reqs

In OMDQ you can check which external requisitions are considered for this MRP type, you can customize a new one for your specific need.

Hope the above clarifies your query.

Regards,

Vivek