Dear Gurus,

How can I display only the critical activities in the project planning board in the gantt chart.

If through the use of filter, pls list down the steps because, i tried but could not.

If there is any other way also, pls share. I think in CNS47 i can use the filter and get the list. But can i see it in planning board??

Regards,

VDS

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi ,

Go to Project planning board then

Edit > Select > All WBS element

then

Edit > Show/Hide > Hide WBS element

Now there will be only activities on screen

Edit > Select > Aactivities

Now apply filter

Basic total float = 0

Execute

and then enter

Only activities with 0 float will be there those r critical activities.

Rgds