on 04-08-2009 7:36 AM
Dear All
In Project system i have created activities under WBS i use backward scheduling but my client requirment was without maintain relationship or any linkage between activity he required activity linkage in gantt chart is it possible pl gave ur input on this
Regards
Hi ,
In gantt chart i.e. Project planning board u can link the activities with the Switch connect mode option. Here u can link the activities just as we do in MS Project. Or u can maintain standard activities with those relation and copy with reference.
Rgds