on 04-08-2009 7:33 AM
Hi
I have 2 projects in my sceanario. One is parent and the other one is child project. Budget is at the 1st level WBSE of Parent project and cost is inccuring at the 2nd level WBSE of the child project.
How can I assign and control assigned costs at the top level of Parent WBSe with controls on budget check.
Regards
thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
dear saqib,
As per my understanding from your question is that you have two separate projects each having separate WBSE. You require the control over budget of one WBSE from parent project where as cost is getting incurred at WBSE from the second project.
In that case you have to settle the WBSE where cost is getting incurred to the top level WBSE from parent project. Also apply the similar budgeting controls at both the WBSE (from parent and child Project).
For settling the cost the projects required to have settlement profile (with settlement allowed to WBS elements). Also settlement rule is required to enter in WBS element with account assignment category as WBS and in settlement receiver should be the top level wbs element of parent project.
regards,
Sudhir kesarkar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi ,
Maintain ur budget on Top level WBS only. Not at bottom level. Then system can control the expense amount of level 2 WBS with refeence to budget amount of level 1.
Rgds
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You can go for Investment Management .
Refer:
http://help.sap.com/saphelp_erp60_sp/helpdata/en/2a/f9f294493111d182b70000e829fbfe/frameset.htm
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.